As Abu Dhabi’s latest icon opens its doors, Gulf Construction delves into its design and construction in a special project report.
01 May 2010
OVER the last three years, visitors and passers-by at one of Abu Dhabi’s newly-developed beachfronts in Al Raha would have watched with great interest as a unique structure rose beside the sea like some futuristic flying saucer poised for take off or coin standing on its diameter.
Now, with the tower nearly complete, they will soon be visiting and admiring this spherical 110-m-high landmark from Aldar Properties, one of Abu Dhabi’s premier real estate developers, when it opens its doors later this year.
Built at a cost of Dh950 million ($258.8 million) and christened ‘HQ’ – as it will be home to Aldar’s headquarters – the tower enters the record books as the first spherical building in the Middle East.
![]() |
|
From concept to completion (top) ... HQ is a new landmark on Abu Dhabi’s skyline. |
Design
The design objective was to achieve a cost-efficient building that allows spatial requirements to be met whilst respecting the form of the building and permitting the creation of the strong visual shape. The design is sufficiently robust to facilitate future fit-outs by tenants and provide significant areas of flexibility where possible.
The building comprises a steel frame rising up to 23 storeys and connected to two large concrete cores to transfer the loads of the exterior weight. It has a diameter of 120.9 m with its width varying from 10 m at ends to 36.4 m in the middle.
![]() |
|
Tight deadlines ... the project team worked closely together, using advanced 3D models developed by Arup. |
![]() |
|
Sleek design ... side angle of HQ. |
Construction
Built to international Grade A standards, HQ sits on reinforced concrete (RC) piling connected to suspended RC slabs. The superstructure comprises RC slipformed core and steel frame while the flooring consists of steel superstructure with composite metal deck floors.
Steel-frame superstructure forms the curved shape of the main façades, laterally braced to two RC slipformed cores with suspended composite metal deck floors.
Various strengths of concrete have been used to suit the application, ranging from C40 to C70.
The external facade comprises a double-glazed, panel façade system with solar-reflective and low-emissivity coatings.
The facade was analysed and glazing options were investigated in order to develop the most efficient strategy for production and construction purposes. A series of studies were carried out in order to find a geometric shape that enables the most efficient unitising of glazing units, while maintaining the aesthetics of the form and shape.
At the concept stage, each facade consisted of 5,821 glazing units with a total of 11,642 individual glazing units. Overall, there are 1,451 sets, each consisting of eight identical glazing units. As a result, it was necessary to increase the unitising of the glazing in the schematic design process.
In adherence to Leed guidelines, the building features extensive use of recyclable materials, and prefabricated elements to ensure minimum waste creation and an automated vacuum waste system – the first of its kind in Abu Dhabi – to aid in recycling waste materials.
Finishes & features
HQ features world-class finishes throughout all common areas incorporating natural materials. The ground floor reception and lift lobbies feature Calacatta marble flooring, skirting, Portuguese limestone wall cladding and suspended plaster-board ceilings.
Typical floor lift lobbies feature Calacatta marble flooring, skirting, glass and stainless steel wall panelling and a suspended plasterboard ceiling.
![]() |
|
Blueprints ... the basement and floors (below). |
Landscaping
The area around HQ has been extensively landscaped with an elliptical-shaped pool at the entrance and two pedestrian paths cutting through the water feature, enhancing the vibrancy of the plaza as well as offering pedestrians a different perspective of the project.
There is continuous paving across the forecourt (warm and cool grey granite tones) and water features. The paving pattern evokes the facade of the building in plan, with the ‘diagrid’ spreading down throughout the plaza and stretching across the landscape.
Clever use has been made of lighting to highlight and enhance the landscape features. Creating an appropriate landscape for the project was no small feat. The design team’s goal was to provide a strong impact that relates to the scale and significance of the building.
![]() |
Challenges
HQ presented a challenge right at the outset of construction because of the high water table in the area. The builders had to drive piles from the ground level and work without the support of a diaphragm wall at the southern elevation.
There were other challenges. The late appointment of the BMU (building maintenance unit) contractor and lack of pre-construction services for this package led to co-ordination tangles with the façade and steelwork interfaces which had to be resolved on site, the spokesman explains. The roof’s unique geometry made it necessary to design a special BMU as well.
![]() |
|
Uninterrupted views ... HQ uses structural diagrids, eliminating the need for internal columns. |
To meet the project’s deadlines, work on HQ continued through the hot and humid summers and in shifts during the months of Ramadan. “The project team worked closely together and this allowed a significant overlap between the design and construction phases,” he explains. “Within three months of the design team’s appointment, piling work had started on the site. The concrete cores were completed within a year, and the steelwork had risen to the fourth floor within 14 months of the launch of construction.”
This collaborative approach allowed lead consultant Arup to design the building with the most efficient means of construction in mind. Concrete elements such as stairs and columns were precast while bathrooms were prefabricated.
“This not only saved time, but also improved quality, because the fitters did not have to work around other parts of the construction,” the spokesman says.
As Aldar gears to open HQ, its designers and builders can take pride in having succeeded in creating a stunning visual icon for Aldar.
But more importantly, behind the superlatives and the plaudits – HQ won the Best Futuristic Design award at the 2008 Building Exchange Conference, and was also a winner at the 2009 Arabian Commercial Property Awards in two categories – lies a functional office tower built to world-class standards that will add to the stature of Abu Dhabi as an international destination for business.