Aldar homes nearly ready

01 November 2017

Aldar Properties of Abu Dhabi is preparing to hand over two of its key residential projects – Ansam and Al Hadeel – to its customers this December.

An Andalusian-style apartment development, Ansam is coming up on the west side of Yas Island, Abu Dhabi. Work is progressing at a steady pace on this project with landscaping due to commence this month (November) while internal final fit-outs are nearing completion.

Also nearing completion is Al Hadeel, located on Al Raha Beach and featuring apartments, townhouses and duplexes. Façade work is now complete and fit-out and landscaping are entering the final stages of completion.

A leading player in the UAE real estate market, Aldar says it continues to make steady progress across all its properties.

 Located on the coast adjacent to Al Bateen, Nareel Island is making steady headway as it moves closer to handover. Infrastructure works are progressing well with road works well advanced and nearing completion.

Similarly, Al Merief in Khalifa City, also being readied for handover, is moving forward with infrastructure work and roadworks at various stages of completion, says the company.

On Reem Island, the main contract has been awarded for The Bridges, a six-building, 1,272-home development that was launched in April last year and sold out within three weeks. Piling works will commence this month.

Meera, which comprises two 25-storey residential towers on Reem Island, continues to make rapid progress. Construction work continues as per the schedule, with the superstructure complete for both buildings, and cladding work under way.

 Elsewhere on Yas Island, at Yas Acres, the flagship golf and waterfront villa and townhouse development on the island’s northern shores, villa construction is under way on all 652 launched villas and townhouses. Construction has also commenced for the services supporting the main roads within the development, says the Abu Dhabi developer.

 Meanwhile, the majority of villas at West Yas, Aldar’s first villa community on Yas Island, are structurally complete across the whole site with remaining construction and various works progressing as per schedule. Over 300 villas are in the final fix stage, ahead of being handed over to customers, it adds.