Friday 15 November 2024
 
»
 
»
Story

Mammoet plays major role in Brazil FPSO project execution

LONDON, February 16, 2022

Mammoet, the global heavy lifting and transport specialist, said it had achieved a major milestone by helping Brazilian offshore construction specialists Estaleiros do Brasil (EBR) complete the engineering, planning and execution of the load-out of seven modules within just a few weeks.
 
These modules were being built in Brazil destined for floating, production, storage and offloading (FPSO) integrations abroad; the challenge was on to have the modules in active production as soon as possible.
 
The modules – some weighing up to 2,200 tonnes each and over 30 million by 18m in size – were to be transferred from the quay to a waiting ship. 
 
According to Mammoet, the Phase One of the project involved the transfer of the first four such modules, followed by the remaining three within Phase Two.
 
The work was not straightforward, however. A challenge presented itself during the first phase, as there were limited feasible jacking points available underneath the module. 
 
These are strengthened areas, built into a module’s design, that allow it to be lifted from underneath by large jacking systems, it stated. 
 
As there was not sufficient time to reinforce the structure of each module so that they could be jacked down using other points, an alternative solution had to be found. It came through innovative use of standard lifting equipment, it stated. 
 
Hydraulic trailers used for transport projects have the ability to raise and lower mechanically, so it was decided that each module would be lowered sequentially, using the hydraulic course of the trailers rather than traditional jacking equipment. 
 
In turn, each module was weighed, jacked-down to the correct grillage height, then loaded-out onto the ship within a precise timeframe. 
 
Despite the novel approach, Mammoet said this methodology allowed the first four modules to be loaded-out in just 12 days instead of the allotted 15. 
 
Phase two of the operation, which included the three final modules, was successfully completed a few months later. During this phase, only the weighing and load-out was required. 
 
To complete this scope, Mammoet's team mobilized the same 96 axle-lines of PST/THP trailers as previously used, a large selection of weighing and auxiliary equipment, and it could mobilize staff from every corner of the Americas to ensure the job was done on time. 
 
During Phase Two, the largest module measured over 29.9m (around 98,000 ft) long and 37.488m (122.9 ft) tall. Again, each module’s weight aligned with expectations, at around 2,200t each.
 
On its key achievement, Mammoet Project Manager Alvaro Campos, said: "One of our greatest challenges was the mobilization time since we were asked to deliver within a very short notice and the required equipment was in various locations across Brazil."
 
"We managed to get everything to site on time thanks to the hard work of a very professional crew and we pulled out a safe execution which was praised many times by our final clients and brought them much relief," he stated.
 
Both phases were effectively delivered for end customers Modec and Cameron/SBM respectively, and all tasks were executed while complying with our customer’s and Mammoet's high safety standards. 
 
Mammoet’s team has vast experience in loading out large modules onto vessels across the globe, most recently a nearly 4,000t topside in Turkmenistan.-TradeArabia News Service



Tags: Brazil | FPSO | Mammoet | project execution |

More Industry, Logistics & Shipping Stories


Markets

calendarCalendar of Events

Partners

4580

Ads

Buy high quality China wholesale Health & Beauty , Electronics, Sports & Outdoors , Computers, Video Games, Toys & Hobbies Cell Phones, Automobiles and other wholesale products directly from reliable Chinese wholesalers or Factories on DHgate.com