Dewa sets world record for gas turbine overhaul

DUBAI, June 17, 2019

Dubai Electricity and Water Authority (Dewa) has broken the world record in major inspection outages by re-engineering the Gas Turbine SGT-4000F overhaul process at the Jebel Ali Power and Desalination Complex.

Dewa succeeded the completion of its major inspection outage within 11 working days compared to 30 working days previously. This allows a 63 per cent reduction in outage duration, leading to increased availability of its gas turbines.

“These gas turbines, along with the steam turbines in the same train, provide 63.2 per cent of Dewa’s gas plant power generation capacity, and 55 per cent of the total thermal energy needed to produce desalinated water that Dewa provides to Dubai,” said Saeed Mohammed Al Tayer, MD & CEO of Dewa.

“This shows the strategic importance of the project to Dewa. In order to ensure its success, a Project Charter was initiated with a clear vision and strategic objectives in line with Dewa’s vision of being a globally leading sustainable innovative corporation.”

The project’s objectives were to strengthen and highlight Dubai's position as a leader in technological transformation. There are a total of 461 similar units worldwide, with 46 in the UAE. The lessons learned from Dewa’s achievement helped global users to use these turbines as a benchmark to improve their operating costs and availability of their services, and improve their environmental footprint.

“Using various innovative ideas and techniques, a team comprised of over 200 members, including 176 field staff, succeeded in reducing the major inspection outage of the unit GTK53 at K Station in October 2018 to 11 working days, breaking the previous world record of 20 days. To affirm the project’s sustainability, the same period was achieved on the unit GTK52 at K Station in April 2019,” said Nasser Lootah, executive vice president of Generation at Dewa.

Since the project’s success, the major inspection outage period over the next 12 years is expected to result in an increase in the availability of high-efficiency units and use by 756 days. In addition, Dewa managed to reduce carbon dioxide emissions by 394,632 tonnes in a year, equivalent to 18.13 million trees. – TradeArabia News Service




Tags: Jebel Ali | Dewa | overhaul | gas turbine | World record |

More Energy, Oil & Gas Stories


Markets

calendarCalendar of Events

Partners

4580

Ads

Buy high quality China wholesale Health & Beauty , Electronics, Sports & Outdoors , Computers, Video Games, Toys & Hobbies Cell Phones, Automobiles and other wholesale products directly from reliable Chinese wholesalers or Factories on DHgate.com