01 December 2019
The Emirates Water and Electricity Company (Ewec) has received bids for its 2 GW solar photovoltaic (PV) independent power producer (IPP) project, to be located in the Al Dhafra region in the emirate.
Ewec is a subsidiary of Abu Dhabi Power Corporation (ADPower) and a leading company in the integrated coordination of planning, purchasing and supply of water and electricity in the Emirate of Abu Dhabi and beyond.
The project tender included the financing, construction, operation and maintenance of the solar plant, including installation of solar PV modules, inverters, connection to the transmission network and associated facilities.
Expected to cover an area of 20 sq km, the plant will be the world’s largest solar PV IPP project, and provide power for up to 110,000 households across the UAE. It will be almost double the size of Ewec’s approximately 1.2 GW ‘Noor Abu Dhabi’ solar plant – currently the largest operational single-project solar PV plant in the world, which commenced its commercial operation in April 2019.
Once operational, the plant will lift Abu Dhabi’s solar power capacity to around 3.2 GW, further reducing the emirate’s carbon dioxide emissions by more than 1.6 million metric tons per year – equal to removing around 330,000 cars from the road – improving efficiency and driving sustainability, while catering for the growth in demand across the UAE.
As part of the tendering process launched in July 2019, an optional bid for significant battery storage was allowed and has resulted in substantial market interest. This added option provided an opportunity to build on the existing 108-MW battery capacity that can last for up to six hours, already operational in Abu Dhabi’s current electricity storage system.
Othman Al Ali, chief executive officer of Ewec, said: “We are delighted to have received positive responses from such internationally recognised entities, demonstrating the utmost confidence in Abu Dhabi’s competitive economy. This year, Ewec has already delivered Noor Abu Dhabi, on time and on budget. We continue to deliver on our ambitious sustainable generation programme, and this new plant is integral to our strategic plan to deliver on the clean energy mix outlined by the UAE Energy Strategy 2050.”
Ewec received 48 expressions of interest from potential bidders for the plant earlier this year, a testament of the trust that international investors have in Abu Dhabi. Out of these expressions of interest, 24 qualified to bid for the project after submitting Statements of Qualification.
The award announcement is expected to take place by Q1 of 2020, following evaluation.