Remraam rises rapidly

01 February 2010

Dubai Properties Group (DPG) has said the prestigious 23.5-million-sq-ft Remraam development has registered another significant milestone with 25 buildings reaching full height as construction rapidly progresses on the five, six and seven-floor residences.

More than 3,000 workers are on site daily with over 50 cranes operating throughout the development as 46 per cent of the superstructure is nearing completion ahead of schedule. In addition, infrastructure work continues across the development’s low-rise residential units.

With more than 85 per cent of excavation and 50 per cent of foundations completed at the site, work has commenced on the construction of roads to service the community that will feature upscale studio, one, two and three-bedroom apartments.

Contractors have commenced interior fit-outs including walls, floor tiles and fixtures. External primer paint is progressing with work continuing on balconies and decorative surfaces.